Evicted and Abandoned

Vietnam

Urban Upgrading Project

Approval Date
Apr. 29, 2004
Status
Closed
Closing Date
Dec. 31, 2014
Amount
$222.5M
Displacement:
Confirmed
People displaced (estimated)
57K
Additional details
  • Environmental category: A (project with high environmental and social risk)
  • The project has a resettlement action plan/abbreviated resettlement plan, which was produced by the time the project was approved.
  • Connected World Bank project(s) with resettlement issues, with a total additional cost of $160,000,000: VN-Urban Upgrading Project Additional Finance
More details at worldbank.org