Uganda Transport Sector Development Project
Approval Date
Dec. 10, 2009
Status
Active
Closing Date
Jan. 31, 2016
Amount
$190M
Displacement:
Confirmed
People displaced (estimated)
12.9K
Additional details
- Environmental category: B (project with medium environmental and social risk)
- The project has a resettlement action plan/abbreviated resettlement plan, which was produced by the time the project was approved.
- Connected World Bank project(s) with resettlement issues, with a total additional cost of $75,000,000: UG-Uganda Transport Sector Project Additional Financing