ShiZheng Railway Project
Approval Date
Jun. 24, 2008
Status
Active
Closing Date
Nov. 30, 2015
Amount
$300M
Displacement:
Confirmed
People displaced (estimated)
150.9K
Additional details
- Environmental category: A (project with high environmental and social risk)
- The project has a resettlement action plan/abbreviated resettlement plan, which was produced by the time the project was approved.
