Evicted and Abandoned

Togo

TG-Integrated Disaster and Land Management

Approval Date
Dec. 20, 2011
Status
Active
Closing Date
Feb. 18, 2016
Amount
$5.5M
Displacement:
Possible
People displaced (estimated)
Unknown

This project was administered by the World Bank but paid through another financier.

Additional details
  • Environmental category: B (project with medium environmental and social risk)
  • The project didn’t have a resettlement action plan/abbreviated resettlement plan as of December 31, 2014 but it had a resettlement policy framework.
  • Connected World Bank project(s) with resettlement issues, with a total additional cost of $7,290,000: TG-Integrated Disaster And Land Management Project
More details at worldbank.org